Ronak Rajendra Mutha
Deedo IDDD-RG17Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 14 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Osian SquareP99000033142 | Saravali | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| DwarkaRaj TowersP99000051888 | Sutarpada | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
Ronak Rajendra Mutha, in questions
Does Ronak Rajendra Mutha finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ronak Rajendra Mutha registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Ronak Rajendra Mutha have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.