Rnd Builders & Developers
Deedo IDDD-8H63Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 13 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| SkylineP52000003774 | Dongari | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| PlatinumP52000004590 | Dongari | Certificate Signed | 30 Dec 2020 | 20 Jan 2022 | +13 mo |
| GalaxyP52000019108 | Dongari | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
Rnd Builders & Developers, in questions
Does Rnd Builders & Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 13 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rnd Builders & Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Rnd Builders & Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
