Rna Builders (Ng)
Deedo IDDD-326KOf 12 registrations whose promised date has arrived, 6 kept it (50%). The rest ran a median 18 mo late.
Delivery record
11 of 19 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 19 registrations
19 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| N G Silver SpringP51700000009 | Mirabhayandar (M Corp.) | Certificate Signed | 15 Dec 2018 | 15 Dec 2018 | On date |
| N G CanaryP51700000320 | Mirabhayandar (M Corp.) | Certificate Signed | 15 Dec 2019 | 15 Dec 2019 | On date |
| N G BavenoP51700000589 | Mirabhayandar (M Corp.) | Certificate Signed | 15 Dec 2019 | 14 Dec 2021 | +24 mo |
| N G Valencia Phase IP51700015519 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
| N G TIVOLI Phase IP51700015568 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| N G Valencia Phase IIP51700016924 | Mirabhayandar (M Corp.) | Certificate Signed | 30 Sep 2020 | 29 Mar 2022 | +18 mo |
| N G Diamond HillP51700018254 | Navghar | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| N G Silver Spring Phase IIP51700018291 | Mira Bhayandar (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| N G Vibrancy Phase IP51700018324 | Navghar | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | On date |
| N G Diamond HillP51700030336 | Navghar | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| N G AvenueP51700031064 | Mira Bhayandar (M Corp.) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| N G Grand EmpireP51700031379 | Navghar | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| N G Grand EmpireP51700031846 | Navghar | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| N G Silver Spring Phase IIIP51700031911 | Mira Bhayandar (M Corp.) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| N G Aroma Phase IP51700032309 | Navghar | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| N G Aroma Phase IIP51700032464 | Navghar | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| N G Ocean PearlP51700032694 | Navghar | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| N G Ocean PearlP51700032807 | Navghar | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
| N G BlissP51700034305 | Mirabhayandar (M Corp.) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Show all 19 registrationsShow fewer
Rna Builders (Ng), in questions
Does Rna Builders (Ng) finish projects on time?
Of 12 MahaRERA registrations whose promised completion date has arrived, 6 kept it (50%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rna Builders (Ng) registered with MahaRERA?
16 projects under 19 MahaRERA registrations; 8 completed on MahaRERA.
Does Rna Builders (Ng) have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.