Rk Group Of Infra

Deedo IDDD-9YA4

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 41 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay41 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Vaishnavi ArcadeP52000015145KaranjadeCertificate Signed30 Sep 202030 Sep 2020On date
Vaishnavi EmperiaP52000018020UranCertificate Signed29 Nov 202729 Nov 2027On date
Vaishnavi ResidencyP52000027201Vadghar (Ct)Certificate Signed30 Jun 202329 Jun 2025+41 mo*

Rk Group Of Infra, in questions

Does Rk Group Of Infra finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 41 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rk Group Of Infra registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Rk Group Of Infra have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology