Company or firm · first RERA registration 2017
River Residency Developers
Deedo IDDD-JGJKOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 46 mo late.
Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay46 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| River Residency Phase IV Building N4P52100012745 | Moshi | Certificate Signed | 28 Aug 2023 | 31 Dec 2027 | +52 mo |
| River Residency Phase IV Building SP52100015059 | Moshi | Certificate Signed | 4 Jan 2023 | 4 Jan 2023 | +46 mo* |
| RR Business CentreP52100024063 | Moshi | Certificate Signed | 30 Dec 2024 | 31 Dec 2027 | +36 mo |
River Residency Developers, in questions
Does River Residency Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 46 mo late. Across Maharashtra, 73% kept their date.
How many projects has River Residency Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does River Residency Developers have MahaRERA regulatory cases?
2 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology