River Residency Developers

Company or firm · 3 projects · 3 MahaRERA registrations

3Projects3 RERA registrations
0Completedas reported on MahaRERA project pages
33%Kept RERA date1 of 3 past their proposed date, not extended
+36 moMedian delayvs RERA proposed date · 2 extended
2Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
River Residency Phase IV Building N4P52100012745Haveli2017Certificate Signed28 Aug 202331 Dec 2027+52 months
River Residency Phase IV Building SP52100015059Haveli2018Certificate Signed4 Jan 20234 Jan 2023On date
RR Business CentreP52100024063Haveli2020Certificate Signed30 Dec 202431 Dec 2027+36 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • River Residency Phase IV Building N4+52 mo
  • River Residency Phase IV Building SOn date
  • RR Business Centre+36 mo

Track record notes

  • 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 52 months, for River Residency Phase IV Building N4 (P52100012745).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology