Company or firm · first RERA registration 2017
Rite Developers Pvt. Ltd
Deedo IDDD-8KNPOf 9 registrations whose promised date has arrived, 2 kept it (22%). The rest ran a median 64 mo late.
Projects99 RERA registrations
Kept RERA date22%Maharashtra: 73%
Median delay64 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases9includes insolvency
7 registrations of 9 ran past the RERA date
Months late against the original RERA promise, per registration
9 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Listed as an NCLT insolvency project | Rite CelestaListed as NCLT project: Rite Celesta | Not on record |
| Listed as an NCLT insolvency project | Rite PrimeListed as NCLT project: Rite Prime | Not on record |
| Listed as an NCLT insolvency project | Rite DivineListed as NCLT project: Rite Divine | Not on record |
| Listed as an NCLT insolvency project | Rite LuxuriaListed as NCLT project: Rite Luxuria | Not on record |
| Listed as an NCLT insolvency project | Rite SkyluxeListed as NCLT project: Rite Skyluxe | Not on record |
| Listed as an NCLT insolvency project | Rite AdventListed as NCLT project: Rite Advent | Not on record |
| Listed as an NCLT insolvency project | Rite PerintoListed as NCLT project: Rite Perinto | Not on record |
| Listed as an NCLT insolvency project | Rite Nectar Phase IIListed as NCLT project: Rite Nectar Phase II | Not on record |
| Listed as an NCLT insolvency project | Rite AspireListed as NCLT project: Rite Aspire | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Rite PerintoP51800005813 | Borivali | Certificate Signed | 30 Mar 2021 | 30 Sep 2022 | +67 mo* |
| Rite LuxuriaP51800006260 | Kurla | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Rite SkyluxeP51800006893 | Kurla | Certificate Signed | 30 Jun 2021 | 30 Dec 2021 | +64 mo* |
| Rite DivineP51800006927 | Borivali | Certificate Signed | 31 Dec 2017 | 31 Dec 2018 | +12 mo |
| Rite AspireP51800009215 | Borivali | Certificate Signed | 30 Jun 2021 | 31 Dec 2023 | +64 mo* |
| Rite AdventP51800009491 | Kurla | Certificate Signed | 30 Mar 2021 | 30 Mar 2022 | +67 mo* |
| Rite PrimeP51800010472 | Andheri | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Rite CelestaP51800004974 | Borivali | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Rite Nectar Phase IIP51800026851 | Borivali | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | +49 mo* |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology