Of 9 registrations whose promised date has arrived, 2 kept it (22%). The rest ran a median 64 mo late.

Projects99 RERA registrations
Kept RERA date22%Maharashtra: 73%
Median delay64 mowhen late
Flats sold, all time0registered sale deeds
Regulatory cases9includes insolvency

7 registrations of 9 ran past the RERA date

Months late against the original RERA promise, per registration

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

CaseProjectDate
Listed as an NCLT insolvency projectRite CelestaListed as NCLT project: Rite CelestaNot on record
Listed as an NCLT insolvency projectRite PrimeListed as NCLT project: Rite PrimeNot on record
Listed as an NCLT insolvency projectRite DivineListed as NCLT project: Rite DivineNot on record
Listed as an NCLT insolvency projectRite LuxuriaListed as NCLT project: Rite LuxuriaNot on record
Listed as an NCLT insolvency projectRite SkyluxeListed as NCLT project: Rite SkyluxeNot on record
Listed as an NCLT insolvency projectRite AdventListed as NCLT project: Rite AdventNot on record
Listed as an NCLT insolvency projectRite PerintoListed as NCLT project: Rite PerintoNot on record
Listed as an NCLT insolvency projectRite Nectar Phase IIListed as NCLT project: Rite Nectar Phase IINot on record
Listed as an NCLT insolvency projectRite AspireListed as NCLT project: Rite AspireNot on record

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rite PerintoP51800005813BorivaliCertificate Signed30 Mar 202130 Sep 2022+67 mo*
Rite LuxuriaP51800006260KurlaCertificate Signed31 Dec 201831 Dec 2019+12 mo
Rite SkyluxeP51800006893KurlaCertificate Signed30 Jun 202130 Dec 2021+64 mo*
Rite DivineP51800006927BorivaliCertificate Signed31 Dec 201731 Dec 2018+12 mo
Rite AspireP51800009215BorivaliCertificate Signed30 Jun 202131 Dec 2023+64 mo*
Rite AdventP51800009491KurlaCertificate Signed30 Mar 202130 Mar 2022+67 mo*
Rite PrimeP51800010472AndheriCertificate Signed31 Dec 201731 Dec 2017On date
Rite CelestaP51800004974BorivaliCertificate Signed31 Dec 201731 Dec 2017On date
Rite Nectar Phase IIP51800026851BorivaliCertificate Signed30 Sep 202230 Sep 2022+49 mo*