RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800005813

Rite Perinto · Borivali, Mumbai Suburban · Rite Developers Pvt. Ltd

Promised for 30 Mar 2021, extended once to 30 Sep 2022 — and that date has passed without the project marked complete on MahaRERA.

5 years and 7 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Mar 2021 to 30 Sep 2022 (1 extension certificate on record).
  • Risk: The latest completion date on record, 30 Sep 2022, has passed.
  • Risk: MahaRERA lists this project among projects in NCLT insolvency proceedings.

Documents 2

Registration certificate14 Aug 2017View
Extension certificate9 Sep 2021View

Orders 1

Listed as an NCLT insolvency project

Listed as NCLT project: Rite Perinto

matched by RERA number

View on MahaRERA

Questions about P51800005813

Is Rite Perinto delayed?

Yes. MahaRERA records a promised completion of 30 Mar 2021, revised to 30 Sep 2022, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800005813. The completion date moved from 30 Mar 2021 to 30 Sep 2022.

Who is the promoter?

MahaRERA records Rite Developers Pvt. Ltd as the promoter of P51800005813.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51800005813.