Company or firm · 8 projects · 8 MahaRERA registrations

Also appears as Rite Developers Pvt. Ltd.

8Projects8 RERA registrations
0Completedas reported on MahaRERA project pages
25%Kept RERA date2 of 8 past their proposed date, not extended
+12 moMedian delayvs RERA proposed date · 6 extended
8Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rite PerintoP51800005813Borivali2017Certificate Signed30 Mar 202130 Sep 2022+18 months
Rite LuxuriaP51800006260Kurla2017Certificate Signed31 Dec 201831 Dec 2019+12 months
Rite SkyluxeP51800006893Kurla2017Certificate Signed30 Jun 202130 Dec 2021+6 months
Rite DivineP51800006927Borivali2017Certificate Signed31 Dec 201731 Dec 2018+12 months
Rite AspireP51800009215Borivali2017Certificate Signed30 Jun 202131 Dec 2023+30 months
Rite AdventP51800009491Kurla2017Certificate Signed30 Mar 202130 Mar 2022+12 months
Rite PrimeP51800010472Andheri2017Certificate Signed31 Dec 201731 Dec 2017On date
Rite CelestaP51800004974Borivali2017Certificate Signed31 Dec 201731 Dec 2017On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rite Perinto+18 mo
  • Rite Luxuria+12 mo
  • Rite Skyluxe+6 mo
  • Rite Divine+12 mo
  • Rite Aspire+30 mo
  • Rite Advent+12 mo
  • Rite PrimeOn date
  • Rite CelestaOn date

Track record notes

  • 2 of 8 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 30 months, for Rite Aspire (P51800009215).
  • MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology