Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P51800006260

Rite Luxuria · Kurla, Mumbai Suburban · Rite Developers Pvt. Ltd

Promised for 31 Dec 2018, extended once to 31 Dec 2019 — and that date has passed without the project marked complete on MahaRERA.

7 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2018 to 31 Dec 2019 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Dec 2019, has passed.
  • Risk: MahaRERA lists this project among projects in NCLT insolvency proceedings.

Documents 2

Registration certificate14 Aug 2017View
Extension certificate4 Jan 2019View

Orders 1

Listed as an NCLT insolvency project

Listed as NCLT project: Rite Luxuria

matched by RERA number

View on MahaRERA

Questions about P51800006260

Is Rite Luxuria delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2018, revised to 31 Dec 2019, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P51800006260. The completion date moved from 31 Dec 2018 to 31 Dec 2019.

Who is the promoter?

MahaRERA records Rite Developers Pvt. Ltd as the promoter of P51800006260.

Is it on any MahaRERA regulatory list?

1 MahaRERA order or list names P51800006260.

Answers are generated from the record.

Data through25 Oct 2026, 01:58SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology