Revive Homes Llp
Deedo IDDD-GVVWOf 4 registrations whose promised date has arrived, 2 kept it (50%). The rest ran a median 4 mo late.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree ApartmentP52100021408 | Pune (M Corp.) | Certificate Signed | 30 Sep 2022 | 30 Sep 2022 | On date |
| Lion Cooperative Housing SocietyP52100028161 | Kothrud | Certificate Signed | 30 Jun 2024 | 30 Jun 2024 | On date |
| Meghalaya Apartment CondominiumP52100053747 | Kothrud | Certificate Signed | 31 Oct 2026 | 28 Feb 2027 | +4 mo |
| Godavari Apartment CondominiumP52100055049 | Pune (M Corp.) | Certificate Signed | 31 May 2026 | 30 Sep 2026 | +6 mo* |
| Swarali Apartments CondominiumP52100078468 | Kothrud | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Revive Homes Llp, in questions
Does Revive Homes Llp finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 2 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Revive Homes Llp registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 2 completed on MahaRERA.
Does Revive Homes Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.