Regency Nirman Ltd
Company or firm · 11 projects · 29 MahaRERA registrations
Projects1129 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date74%17 of 23 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 6 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Regency AntiliaP51700002735 | Ulhasnagar (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 30 Jun 2019 | +6 months |
| Regency SarvamP51700002824 | Titwala | 2017 | Not reported | 31 Aug 2018 | — | On date |
| Regency AntiliaP51700002911 | Ulhasnagar (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 30 Jun 2019 | +6 months |
| Regency Classic Wing B2P52100005014 | Pune (M Corp.) | 2017 | Not reported | 30 Jun 2022 | — | On date |
| Regency SarvamP51700007066 | Titwala | 2017 | Not reported | 30 Jun 2018 | — | On date |
| Regency SarvamP51700007704 | Titwala | 2017 | Not reported | 31 Dec 2019 | — | On date |
| Regency AntiliaP51700008116 | Ulhasnagar (M Corp.) | 2017 | Not reported | 30 Jun 2019 | 29 Dec 2020 | +18 months |
| Regency AnantamP51700017874 | Dawadi | 2018 | Not reported | 30 Mar 2022 | — | On date |
| Regency SarvamP51700019211 | Titwala | 2019 | Not reported | 30 May 2022 | — | On date |
| Regency AnantamP51700020186 | Dawadi | 2019 | Not reported | 28 Aug 2022 | — | On date |
| Regency AnantamP51700020194 | Dawadi | 2019 | Not reported | 30 Mar 2024 | — | On date |
| Regency AntiliaP51700023854 | Ulhasnagar (M Corp.) | 2020 | Not reported | 30 Jun 2022 | 30 Jun 2023 | +12 months |
| Regency Antilia Phase V AvanaP51700026760 | Ulhasnagar (M Corp.) | 2020 | Not reported | 30 Oct 2024 | — | On date |
| Regency SarvamP51700029930 | Titwala | 2021 | Not reported | 30 Nov 2024 | — | On date |
| Regency LuxuriaP51700031251 | Kalyandombivali (M Corp.) | 2021 | Not reported | 30 Sep 2025 | 31 Dec 2025 | +3 months |
| Regency Antilia Phase VI AvanaP51700032759 | Ulhasnagar (M Corp.) | 2022 | Not reported | 30 Nov 2025 | — | On date |
| Regency AntiliaP51700032863 | Ulhasnagar (M Corp.) | 2022 | Not reported | 31 Mar 2025 | 30 Sep 2025 | +6 months |
| Regency AnantamP51700033477 | Dawadi | 2022 | Not reported | 31 Aug 2023 | — | On date |
| Regency AnantamP51700033506 | Dawadi | 2022 | Not reported | 31 Aug 2023 | — | On date |
| Regency AnantamP51700049211 | Dawadi | 2023 | Not reported | 31 Aug 2023 | — | On date |
| Regency OnyxP51700049723 | Kalyan-Dombivali (M Corp.) | 2023 | Not reported | 30 Jun 2025 | — | On date |
| Regency AntiliaP51700052485 | Ulhasnagar (M Corp.) | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Regency LuxuriaP51700053314 | Kalyandombivali (M Corp.) | 2023 | Not reported | 31 Dec 2026 | — | On date |
| Regency SapphireP51700053596 | Dawadi | 2023 | Not reported | 30 Jun 2026 | — | On date |
| Regency Anantam Nxt Phase IP51700055848 | Dawadi | 2024 | Not reported | 31 Dec 2028 | — | On date |
| Regency Sarvam Phase 13P51700076860 | Manda | 2024 | Not reported | 31 Dec 2025 | — | On date |
| Regency LuxuriaP51700078991 | Kalyandombivali (M Corp.) | 2025 | Not reported | 30 Jun 2028 | — | On date |
| Regency AntiliaPR1333032502202 | Ulhasnagar (M Corp.) | 2026 | Not reported | 30 Apr 2028 | — | On date |
| Regency AntiliaPR1335052502791 | Ulhasnagar (M Corp.) | 2026 | Not reported | 30 Apr 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 17 of 23 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 18 months, for Regency Antilia (P51700008116).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology