Of 3 registrations whose promised date has arrived, 1 kept it (33%). The rest ran a median 18 mo late — longer than Maharashtra's 4 mo.

Projects24 RERA registrations
Kept RERA date33%Maharashtra: 73%
Median delay18 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Regency PalmsP52000021191Navi Mumbai Panvel Rigardh (Ct)Certificate Signed1 Jun 20241 Jun 2025+12 mo
Regency PalmsP52000021209Navi Mumbai Panvel Rigardh (Ct)Certificate Signed1 Jun 202331 May 2025+23 mo
Regency PalmsP51700046103NerulCertificate Signed31 May 202431 May 2024On date
Regency PalmsP51700046381NerulCertificate Signed31 Dec 202631 Dec 2026On date

Regency Inc, in questions

Does Regency Inc finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 1 kept it (33%). The rest ran a median 18 mo late. Across Maharashtra, 73% kept their date.

How many projects has Regency Inc registered with MahaRERA?

2 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Regency Inc have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology