Skip to content
Individual promoter · first RERA registration 2020

Ravindra Balasaheb Kharde

Deedo IDDD-2ZM3

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 53 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay53 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai SurajP52200026946Ahmadnagar (M Corp.)Certificate Signed30 Jun 202230 Jun 2022+53 mo*

Ravindra Balasaheb Kharde, in questions

Does Ravindra Balasaheb Kharde finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 53 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ravindra Balasaheb Kharde registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Ravindra Balasaheb Kharde have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology