Ravima Developer
Deedo IDDD-9EZ6Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Newton Homes Tathawade Phase IP52100031983 | Tathwade | Certificate Signed | 30 Apr 2025 | 30 Nov 2025 | +19 mo* |
| Newton Homes Tathawade Phase IIP52100052803 | Tathwade | Certificate Signed | 30 Dec 2028 | 30 Apr 2029 | +4 mo |
| The Work Club HadapsarP52100053032 | Hadapsar | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Newton Homes Hadapsar Near Runwal Seagull Phase IIP52100077513 | Hadapsar | Certificate Signed | 31 May 2028 | 30 Sep 2028 | +4 mo |
Ravima Developer, in questions
Does Ravima Developer finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ravima Developer registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Ravima Developer have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.