Ravie Khilumal Ochanni
Deedo IDDD-CK0QOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Balboa Avenue Phase 1P52100012041 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 15 Jan 2018 | 15 Jan 2018 | On date |
| Star VistaP52100026112 | Ravet | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | +38 mo* |
| Star VistaP52100031091 | Ravet | Certificate Signed | 30 Sep 2026 | 30 Jan 2027 | +4 mo |
| Star Vista - MHADAP52100080257 | Ravet | Certificate Signed | 30 Sep 2026 | 30 Sep 2026 | +2 mo* |
Ravie Khilumal Ochanni, in questions
Does Ravie Khilumal Ochanni finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Ravie Khilumal Ochanni registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Ravie Khilumal Ochanni have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.