Ravi Developments

Company or firm · 11 projects · 12 MahaRERA registrations

Projects1112 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date57%4 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases1MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Gaurav SaffronP51700003472Mirabhayandar (M Corp.)2017Not reported30 Dec 202230 Jun 2026+42 months
Gaurav CrestP51700004316Mirabhayandar (M Corp.)2017Not reported30 Dec 202330 Jun 2026+30 months
Gaurav ExcellencyP51700006232Mira Bhayandar (M Corp.)2017Not reported31 Mar 2027—On date
Gaurav EnclaveP51700007276Mira Bhayandar (M Corp.)2017Not reported31 Dec 2028—On date
Poonam Estate Cl 2 BlgP51700008166Mirabhayandar (M Corp.)2017Not reported30 Jun 2019—On date
Poonam Estate Cl 2 BlgP51700009072Mirabhayandar (M Corp.)2017Not reported31 Mar 2018—On date
Shubh AtikaP51700009680Mirabhayandar (M Corp.)2017Not reported30 Dec 202329 Dec 2024+12 months
Gaurav AsterP51700011796Mira Bhayandar (M Corp.)2017Not reported31 Dec 2026—On date
Poonam Estate Mhada Bldg No 8 And 9P51700011797Mirabhayandar (M Corp.)2017Not reported31 Dec 2017—On date
Gaurav Woods IIP51800011407Mira Bhayandar (M Corp.)2017Not reported31 Dec 2028—On date
Blue BellP51700018976Mirabhayandar (M Corp.)2018Not reported30 Dec 2022—On date
RD RoyaltonPR1330002601453Ghodbunder2026Not reported31 Dec 2028—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Gaurav Saffron+42 mo
  • Gaurav Crest+30 mo
  • Gaurav ExcellencyOn date
  • Gaurav EnclaveOn date
  • Poonam Estate Cl 2 BlgOn date
  • Poonam Estate Cl 2 BlgOn date
  • Shubh Atika+12 mo
  • Gaurav AsterOn date
  • Poonam Estate Mhada Bldg No 8 And 9On date
  • Gaurav Woods IIOn date
  • Blue BellOn date
  • RD RoyaltonOn date

Track record notes

  • 4 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 42 months, for Gaurav Saffron (P51700003472).

Regulatory cases across projects

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology