Ravi Developments
Company or firm · 11 projects · 12 MahaRERA registrations
Projects1112 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date57%4 of 7 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 3 extended
Regulatory cases1MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Gaurav SaffronP51700003472 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Dec 2022 | 30 Jun 2026 | +42 months |
| Gaurav CrestP51700004316 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Dec 2023 | 30 Jun 2026 | +30 months |
| Gaurav ExcellencyP51700006232 | Mira Bhayandar (M Corp.) | 2017 | Not reported | 31 Mar 2027 | — | On date |
| Gaurav EnclaveP51700007276 | Mira Bhayandar (M Corp.) | 2017 | Not reported | 31 Dec 2028 | — | On date |
| Poonam Estate Cl 2 BlgP51700008166 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Jun 2019 | — | On date |
| Poonam Estate Cl 2 BlgP51700009072 | Mirabhayandar (M Corp.) | 2017 | Not reported | 31 Mar 2018 | — | On date |
| Shubh AtikaP51700009680 | Mirabhayandar (M Corp.) | 2017 | Not reported | 30 Dec 2023 | 29 Dec 2024 | +12 months |
| Gaurav AsterP51700011796 | Mira Bhayandar (M Corp.) | 2017 | Not reported | 31 Dec 2026 | — | On date |
| Poonam Estate Mhada Bldg No 8 And 9P51700011797 | Mirabhayandar (M Corp.) | 2017 | Not reported | 31 Dec 2017 | — | On date |
| Gaurav Woods IIP51800011407 | Mira Bhayandar (M Corp.) | 2017 | Not reported | 31 Dec 2028 | — | On date |
| Blue BellP51700018976 | Mirabhayandar (M Corp.) | 2018 | Not reported | 30 Dec 2022 | — | On date |
| RD RoyaltonPR1330002601453 | Ghodbunder | 2026 | Not reported | 31 Dec 2028 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 42 months, for Gaurav Saffron (P51700003472).
Regulatory cases across projects
- Quarterly progress report not filedQuarterly progress report not filed: GAURAV WOODS II · Gaurav Woods II · P51800011407
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology