Company or firm · first RERA registration 2021

Rati Builders And Developers

Deedo IDDD-2QE1

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 20 mo late.

Projects33 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay20 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
ParasmaiP52000027727UlaweCertificate Signed30 Jun 202430 Jun 2024+29 mo*
Rati OmkaraP52000051763WahalCertificate Signed31 Dec 202631 Dec 2026On date
Rati VighnartaP52000077197WahalCertificate Signed31 Dec 202531 Dec 2025+11 mo*

Rati Builders And Developers, in questions

Does Rati Builders And Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 20 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rati Builders And Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.

Does Rati Builders And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology