Rashmi Housing Private Limited

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases4MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Rashmi Yug LataP51700007534Mira Bhayandar (M Corp.)2017Not reported30 Jun 2024—On date
Rashmi Hill ViewP99000008810Vasai Virar City (M Corp)2017Not reported30 Dec 2022—On date
Rashmi SarveshP51700011990Thane2017Not reported30 Jun 2023—On date
PANTNAGAR SNEHDEEP CHS LtdP51800015452Kurla2018Not reported30 Mar 2023—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Rashmi Yug LataOn date
  • Rashmi Hill ViewOn date
  • Rashmi SarveshOn date
  • PANTNAGAR SNEHDEEP CHS LtdOn date

Track record notes

  • 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.

Regulatory cases across projects