Rare Townships Private Limited

Company or firm · 16 projects · 16 MahaRERA registrations

16Projects16 RERA registrations
0Completedas reported on MahaRERA project pages
79%Kept RERA date11 of 14 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Manhattan Residency (A4) - 15th to 18th FloorP51800000733Ghatkopar2017Not reported30 Jun 2026—On date
Atlanta Heights (A3) - 15th to 18th FloorP51800000756Kurla2017Not reported4 Feb 2026—On date
Atlanta Heights (A3) - 19th FloorP51800000923Ghatkopar2017Not reported30 Jun 2026—On date
Houston Residency (A2) - 19th floorP51800000933Kurla2017Not reported4 Feb 2026—On date
Houston Residency (A2) - 15th to 18th floorP51800000934Ghatkopar2017Not reported30 Apr 2026—On date
Detroit Residency (A5) - 19th FloorP51800000935Kurla2017Not reported30 Dec 202430 Dec 2025+12 months
Houston Residency (A2) - upto 14th floorP51800000937Ghatkopar2017Not reported30 Apr 2026—On date
India International Tower (A6) - upto 13th FloorP51800001034Kurla2017Not reported30 Dec 202630 Dec 2027+12 months
North Sea Heights (A1) - 15th to 18th floorP51800001036Ghatkopar2017Not reported30 Jun 2026—On date
North Sea Heights (A1) - 19th floorP51800001037Ghatkopar2017Not reported30 Jun 2026—On date
North Sea Heights (A1) - upto 14th floorP51800001041Ghatkopar2017Not reported30 Jun 2026—On date
Detroit Residency (A5) - 15th to 18th FloorP51800001063Kurla2017Not reported30 Dec 202430 Dec 2025+12 months
Atlanta Heights (A3) - upto 14th FloorP51800001079Kurla2017Not reported30 Jun 2026—On date
Detroit Residency (A5) - upto 14th FloorP51800001133Kurla2017Not reported30 Dec 202430 Dec 2025+12 months
Manhattan Residency (A4) - upto 14th FloorP51800001229Ghatkopar2017Not reported30 Jun 2026—On date
India International Tower (A6) - 14th to 19th floorP51800001357Kurla2017Not reported30 Dec 202730 Dec 2027On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Manhattan Residency (A4) - 15th to 18th FloorOn date
  • Atlanta Heights (A3) - 15th to 18th FloorOn date
  • Atlanta Heights (A3) - 19th FloorOn date
  • Houston Residency (A2) - 19th floorOn date
  • Houston Residency (A2) - 15th to 18th floorOn date
  • Detroit Residency (A5) - 19th Floor+12 mo
  • Houston Residency (A2) - upto 14th floorOn date
  • India International Tower (A6) - upto 13th Floor+12 mo
  • North Sea Heights (A1) - 15th to 18th floorOn date
  • North Sea Heights (A1) - 19th floorOn date
  • North Sea Heights (A1) - upto 14th floorOn date
  • Detroit Residency (A5) - 15th to 18th Floor+12 mo
  • Atlanta Heights (A3) - upto 14th FloorOn date
  • Detroit Residency (A5) - upto 14th Floor+12 mo
  • Manhattan Residency (A4) - upto 14th FloorOn date
  • India International Tower (A6) - 14th to 19th floorOn date

Track record notes

  • 11 of 14 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 12 months, for Detroit Residency (A5) - 19th Floor (P51800000935).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology