Company or firm · first RERA registration 2020

Ranas Construction

Deedo IDDD-44DE

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 25 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay25 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mannat ResidencyP51700023930Ulhasnagar (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Mannat AvenueP51700047249Ulhasnagar (M Corp.)Certificate Signed31 Oct 202431 Oct 2024+25 mo*

Ranas Construction, in questions

Does Ranas Construction finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 25 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ranas Construction registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Ranas Construction have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology