Ramchandra Lalsingh Kharpuriya

Deedo IDDD-CB7V

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 11 mo late.

Projects12 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
MerakiP52000045659ShilarCertificate Signed30 Jun 202530 Jun 2025+17 mo*
MerakiP52000047706ShilarCertificate Signed31 Dec 202630 Apr 2027+4 mo

Ramchandra Lalsingh Kharpuriya, in questions

Does Ramchandra Lalsingh Kharpuriya finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Ramchandra Lalsingh Kharpuriya registered with MahaRERA?

1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Ramchandra Lalsingh Kharpuriya have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology