Company or firm · first RERA registration 2020

Rama Synergy Spaces

Deedo IDDD-Z6JG

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 23 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay23 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Metro Life Optima ResidencesP52100026255TathwadeCertificate Signed31 Dec 202431 Dec 2024+23 mo*

Rama Synergy Spaces, in questions

Does Rama Synergy Spaces finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 23 mo late. Across Maharashtra, 73% kept their date.

How many projects has Rama Synergy Spaces registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Rama Synergy Spaces have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology