Rajendra Suresh Jain
Deedo IDDD-9274Of 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 24 mo late.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Runal Gateway Phase 1P52100002021 | Kiwale | Certificate Signed | 30 Dec 2019 | 29 Dec 2021 | +24 mo |
| Runal ElanzaP52100002255 | Haveli | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| Runal SpacioP52100019467 | Kiwale | Certificate Signed | 30 Dec 2022 | 30 Dec 2023 | +12 mo |
| Runal Gateway Phase - IIP52100019500 | Kiwale | Certificate Signed | 30 Mar 2021 | 30 Mar 2021 | On date |
| Runal Gateway Phase IIIP52100024155 | Kiwale | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
Rajendra Suresh Jain, in questions
Does Rajendra Suresh Jain finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Rajendra Suresh Jain registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Rajendra Suresh Jain have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.