Rai Residency Private Limited
Company or firm · 16 projects · 16 MahaRERA registrations · 2 reported completed
16Projects16 RERA registrations
2Completedas reported on MahaRERA project pages
80%Kept RERA date8 of 10 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 6 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| YASHWANT HEIGHTS C WingP51700008574 | Tisgaon | 2017 | Completed | 31 Mar 2018 | 31 Jan 2020 | +22 months |
| RAI S HERITAGE D WingP51700009044 | Katemanevali | 2017 | Completed | 31 Dec 2018 | — | On date |
| Rai Valley A B C WingP51700011390 | Katemanevali | 2017 | Certificate Signed | 31 Dec 2017 | 31 Dec 2017 | On date |
| Sudama EnclaveP51700011514 | Tisgaon | 2017 | Certificate Signed | 30 Jun 2018 | 30 Jun 2018 | On date |
| Rai ParadiseP51700012449 | Katemanevali | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Rai s AARAGYAP51700017230 | Kalyan | 2018 | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| RAI s VRUNDAVANP51700017255 | Kalyan | 2018 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Rai s TulipP51700018533 | Tisgaon | 2018 | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Rai s HeavenP51700018559 | Tisgaon | 2018 | Certificate Signed | 30 Dec 2030 | 30 Apr 2031 | +4 months |
| Gopika EnclaveP51700023565 | Tisgaon | 2019 | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Kairali ParkP51700026352 | Katemanevali | 2020 | Certificate Signed | 30 Jun 2024 | 29 Jan 2025 | +7 months |
| Yashwant Heights Phase IIP51700030946 | Tisgaon | 2021 | Certificate Signed | 31 May 2023 | 31 May 2023 | On date |
| AshtamiP51700049225 | Tisgaon | 2023 | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 months |
| Shree Om ShivshaktiP51700054699 | Tisgaon | 2024 | Certificate Signed | 31 Dec 2026 | 31 Dec 2026 | On date |
| Rai S GalaxyP51700055364 | Tisgaon | 2024 | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 months |
| Sai Leela Galaxy D WingPR1330002500931 | Tisgaon | 2025 | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 months |
Show all 16 registrationsShow fewer
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Show all 16 registrations
Track record notes
- 8 of 10 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 22 months, for YASHWANT HEIGHTS C Wing (P51700008574).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology