Raghukul Constructions Private Limited

Company or firm · 5 projects · 5 MahaRERA registrations

Projects55 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date—no proposed date has passed yet
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
DigvijayaP50500047723Nagpur (M Corp.)2022Not reported15 Sep 2027—On date
Kalyani SamadhanP50500076896Nagpur (M Corp.)2024Not reported15 Apr 2030—On date
BinapaniP50500077413Nagpur (M Corp.)2024Active15 Jul 2030—On date
ShantaiPR1190002500651Nagpur (M Corp.)2025Not reported1 Jul 2032—On date
Devasheesh (18 Bless) ApartmentPR1190002601502Nagpur (M Corp.)2026Not reported30 Apr 2032—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • DigvijayaOn date
  • Kalyani SamadhanOn date
  • BinapaniOn date
  • ShantaiOn date
  • Devasheesh (18 Bless) ApartmentOn date

Track record notes

  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology