Company or firm · 2 projects · 2 MahaRERA registrations

Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%2 of 2 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Deogiri PuramP51500008456Aurangabad (M Corp.)2017Lapsed19 Feb 2021—On date
Deogiri Puram Phase 2P51500028256Aurangabad2021Not reported14 Dec 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Deogiri PuramOn date
  • Deogiri Puram Phase 2On date

Track record notes

  • 2 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.