Skip to content
Company or firm · first RERA registration 2018

R K Builders & Developers

Deedo IDDD-VWX0

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 3 mo late — shorter than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay3 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Raghunath NagarP51100015354Nanded Waghala (M Corp.)Completed30 Dec 2023—On date
R R Tilak NagarP51100031887Nanded Waghala (M Corp.)Certificate Signed31 Dec 202331 Mar 2024+3 mo
RenukaP51100034604Nanded Waghala (M Corp.)Certificate Signed31 Dec 202431 Dec 2024On date

R K Builders & Developers, in questions

Does R K Builders & Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 3 mo late. Across Maharashtra, 73% kept their date.

How many projects has R K Builders & Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does R K Builders & Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology