Deedo IDDD-YA0Y

Of 7 registrations whose promised date has arrived, 5 kept it (71%). The rest ran a median 3 mo late.

Projects1111 RERA registrations
Kept RERA date71%Maharashtra: 73%
Median delay3 mowhen late
First sales on record30registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 11 registrations with dates moved or missed their RERA date · months late against the original promise

11 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Prathamesh SylvaticaP52100003074BanerCertificate Signed31 Dec 201931 Dec 2019On date
Prathamesh Novellus building of chaya heights CHSP52100003707KothrudCertificate Signed31 Jul 201831 Jul 2018On date
Prathamesh AmrutyogP52100017592Pune (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Prathamesh Shreyas Building Of Shree Mukundnagar Sahakari Gruharachana Sanstha MaryaditP52100021628Pune (M Corp.)Certificate Signed30 Sep 202330 Sep 2023On date
Prathamesh Anant Building Of Bhargav Chs LtdP52100023511ParvatiCertificate Signed30 Jun 202330 Jun 2023On date
Prathamesh AshishP52100034420GultekadiCertificate Signed31 Dec 202331 Mar 2024+3 mo
Prathamesh Sanskruti building of Abhinav Apartments AssociationP52100034849Sadashiv PethCertificate Signed31 Oct 202631 Oct 2026+1 mo*
Prathamesh YashodhamP52100080692GultekadiCertificate Signed31 Dec 202830 Apr 2029+4 mo
Prathamesh AakrutiPR1260002503077KothrudCertificate Signed30 Apr 202930 Apr 2029On date
Amardeep Jyoti CHSLPR1260002600208Erandwana NorthCertificate Signed30 Oct 203030 Oct 2030On date
Janaki PrasadPR1260002600340ParvatiCertificate Signed30 Apr 202930 Apr 2029On date
Show all 11 registrationsShow fewer

Prathamesh Constructions, in questions

Does Prathamesh Constructions finish projects on time?

Of 7 MahaRERA registrations whose promised completion date has arrived, 5 kept it (71%). The rest ran a median 3 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prathamesh Constructions registered with MahaRERA?

11 projects under 11 MahaRERA registrations; 6 completed on MahaRERA.

Does Prathamesh Constructions have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology