Company or firm · first RERA registration 2020

Pratham Yash Builders

Deedo IDDD-JH5M

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.

Projects23 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay4 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Pratham Yash VrindavanP52100026265CharholiCertificate Signed31 Oct 202631 Oct 2026+1 mo*
Pratham Yash VrindavanP52100053316CharholiCertificate Signed30 Sep 202730 Jan 2028+4 mo
Prathamyash E BuildingPR1260002601162ChovisawadiCertificate Signed30 Apr 202730 Aug 2027+4 mo

Pratham Yash Builders, in questions

Does Pratham Yash Builders finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Pratham Yash Builders registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Pratham Yash Builders have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology