Pratham Yash Builders
Deedo IDDD-JH5MOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 4 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pratham Yash VrindavanP52100026265 | Charholi | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| Pratham Yash VrindavanP52100053316 | Charholi | Certificate Signed | 30 Sep 2027 | 30 Jan 2028 | +4 mo |
| Prathamyash E BuildingPR1260002601162 | Chovisawadi | Certificate Signed | 30 Apr 2027 | 30 Aug 2027 | +4 mo |
Pratham Yash Builders, in questions
Does Pratham Yash Builders finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pratham Yash Builders registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Pratham Yash Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.