Prasad Janardan Marathe

Deedo IDDD-V006

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay12 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Kadamb Apartments A and BP52000028837GoregaonCertificate Signed15 Jun 202215 Jun 2023+12 mo

Prasad Janardan Marathe, in questions

Does Prasad Janardan Marathe finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.

How many projects has Prasad Janardan Marathe registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Prasad Janardan Marathe have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology