Is this project on time and in good standing?

Projects: P + 11 digits (or two letters + 13 digits, like PR1260002500851). Agents: A + 11 digits.

RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52000028837

Kadamb Apartments A and B · Goregaon, Raigarh · Prasad Janardan Marathe

Promised for 15 Jun 2022, extended once to 15 Jun 2023 — and that date has passed without the project marked complete on MahaRERA.

4 years and 4 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 15 Jun 2022 to 15 Jun 2023 (1 extension certificate on record).
  • Risk: The latest completion date on record, 15 Jun 2023, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate8 Sep 2021View
Extension certificate27 Jun 2022View

Orders 0

No MahaRERA order or list names this number.

Questions about P52000028837

Is Kadamb Apartments A and B delayed?

Yes. MahaRERA records a promised completion of 15 Jun 2022, revised to 15 Jun 2023, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52000028837. The completion date moved from 15 Jun 2022 to 15 Jun 2023.

Who is the promoter?

MahaRERA records Prasad Janardan Marathe as the promoter of P52000028837.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52000028837.

Answers are generated from the record.

Data through30 Oct 2026, 02:35SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersReport a problemMethodology