Prakash Rajaram Jaitapkar
Deedo IDDD-PWS2Of 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Jaitapkarwadi Phase IIP52900003896 | Oras Bk. | Certificate Signed | 30 May 2019 | 30 May 2019 | On date |
| Jaitapkarwadi Phase IIIP52900026560 | Oras Bk. | Certificate Signed | 26 Jun 2029 | 26 Oct 2029 | +4 mo |
| Mahalaxmi ResidencyP52900053039 | Kudal (Ct) | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
Prakash Rajaram Jaitapkar, in questions
Does Prakash Rajaram Jaitapkar finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Prakash Rajaram Jaitapkar registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Prakash Rajaram Jaitapkar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.