Pragati Constructions
Deedo IDDD-ZFXJOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 60 mo late.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Satkar TowerP51700012168 | Katemanevali | Certificate Signed | 31 Dec 2019 | 31 Dec 2024 | +83 mo* |
| Om Darshan HeightsP51700021003 | Katemanevali | Certificate Signed | 22 Oct 2023 | 22 Oct 2023 | +37 mo* |
| Samarth AlturaPR1330002601411 | Katemanevali | Certificate Signed | 31 Dec 2031 | 31 Dec 2031 | On date |
Pragati Constructions, in questions
Does Pragati Constructions finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 60 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pragati Constructions registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Pragati Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.