Patel Group & Co
Deedo IDDD-22PXOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 35 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Patel ColossusP51700008709 | Kalyan | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| Patel ColossusP51700009981 | Kalyan | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | +35 mo* |
| Patel ColossusP51700010242 | Kalyan | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
| Patel MountP51700048299 | Chikanghar | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Patel Group & Co, in questions
Does Patel Group & Co finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 35 mo late. Across Maharashtra, 73% kept their date.
How many projects has Patel Group & Co registered with MahaRERA?
2 projects under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Patel Group & Co have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.