Parulekar Realty LLP
Deedo IDDD-WEZ9Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.
Delivery record
4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shri DeodootP52100051833 | Kothrud | Certificate Signed | 31 Oct 2026 | 28 Feb 2027 | +4 mo |
| GharondaP52100053024 | Erandwana | Certificate Signed | 31 Jul 2026 | 31 Jul 2026 | On date |
| Nav ShailajaP52100054274 | Kothrud | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Vaishnavi ApartmentP52100078349 | Kothrud | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| SarthakP52100078494 | Kothrud | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Parulekar Realty LLP, in questions
Does Parulekar Realty LLP finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Parulekar Realty LLP registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.
Does Parulekar Realty LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.