Parth Developers

Company or firm · 6 projects · 6 MahaRERA registrations

Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%4 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Parth Enclave E BuildingP52100000678Karve Nagar2017Not reported31 Aug 2018—On date
Bhagat HeritageP52000016262Kamothe2018Not reported30 May 2024—On date
Amar Serenity Wing E Lig/Mig BuildingP52100018202Pashan2018Not reported31 Oct 201930 Oct 2021+24 months
Parth Enclave Building FP52100025566Karve Nagar2020Not reported30 Sep 202324 Mar 2025+18 months
M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc LtdP51800032481Kurla2022Not reported31 Dec 2025—On date
Bhagat Parth SerenityP52000054454Kamothe2024Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Parth Enclave E BuildingOn date
  • Bhagat HeritageOn date
  • Amar Serenity Wing E Lig/Mig Building+24 mo
  • Parth Enclave Building F+18 mo
  • M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc LtdOn date
  • Bhagat Parth SerenityOn date

Track record notes

  • 4 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 24 months, for Amar Serenity Wing E Lig/Mig Building (P52100018202).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology