Company or firm · 6 projects · 6 MahaRERA registrations
Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date67%4 of 6 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Parth Enclave E BuildingP52100000678 | Karve Nagar | 2017 | Not reported | 31 Aug 2018 | — | On date |
| Bhagat HeritageP52000016262 | Kamothe | 2018 | Not reported | 30 May 2024 | — | On date |
| Amar Serenity Wing E Lig/Mig BuildingP52100018202 | Pashan | 2018 | Not reported | 31 Oct 2019 | 30 Oct 2021 | +24 months |
| Parth Enclave Building FP52100025566 | Karve Nagar | 2020 | Not reported | 30 Sep 2023 | 24 Mar 2025 | +18 months |
| M/S Shri Sai Lata Flat Owners Co-Op Hsg Soc LtdP51800032481 | Kurla | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Bhagat Parth SerenityP52000054454 | Kamothe | 2024 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 6 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 24 months, for Amar Serenity Wing E Lig/Mig Building (P52100018202).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology