Parth Developers
Deedo IDDD-232ROf 6 registrations whose promised date has arrived, 2 kept it (33%). The rest ran a median 15 mo late.
Delivery record
4 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Parth Enclave E BuildingP52100000678 | Karve Nagar | Certificate Signed | 31 Aug 2018 | 31 Aug 2018 | On date |
| Bhagat HeritageP52000016262 | Kamothe | Certificate Signed | 30 May 2024 | 30 May 2024 | On date |
| Amar Serenity Wing E LIG/MIG BuildingP52100018202 | Pashan | Certificate Signed | 31 Oct 2019 | 30 Oct 2021 | +24 mo |
| Parth Enclave Building FP52100025566 | Karve Nagar | Certificate Signed | 30 Sep 2023 | 24 Mar 2025 | +18 mo |
| Shri Sai Lata Flat Owners Co-Op Hsg Soc LtdP51800032481 | Kurla | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Bhagat Parth SerenityP52000054454 | Kamothe | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
Parth Developers, in questions
Does Parth Developers finish projects on time?
Of 6 MahaRERA registrations whose promised completion date has arrived, 2 kept it (33%). The rest ran a median 15 mo late. Across Maharashtra, 73% kept their date.
How many projects has Parth Developers registered with MahaRERA?
6 projects under 6 MahaRERA registrations; 4 completed on MahaRERA.
Does Parth Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.