Of 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects44 RERA registrations
Kept RERA date75%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record108registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
VedaP52100003939DhanoriCertificate Signed31 Mar 201831 Jul 2018+4 mo
SignetP52100017261DhanoriCertificate Signed31 Dec 201931 Dec 2019On date
RagaP52100025758LohgaonCertificate Signed30 Sep 202230 Sep 2022On date
TejasP52100034114LohgaonCompleted31 Jul 202431 Jul 2024On date

Parshwa Developers, in questions

Does Parshwa Developers finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Parshwa Developers registered with MahaRERA?

4 projects under 4 MahaRERA registrations; 4 completed on MahaRERA.

Does Parshwa Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology