Pankaj Developers
Deedo IDDD-EHW9Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 33 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 6 registrations with dates moved or missed their RERA date · months late against the original promise
6 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Pankaj AasmaanP52100005649 | Lahagaon | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Pankaj AasmaanP52100009665 | Lahagaon | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Pankaj AasmaanP52100016512 | Lohgaon | Certificate Signed | 1 Oct 2021 | 31 Dec 2026 | +62 mo |
| Pankaj AasmaanP52100023607 | Lohgaon | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
| Pankaj Aasmaan Phase VP52100023613 | Lohgaon | Certificate Signed | 30 Dec 2026 | 30 Dec 2026 | On date |
| Pankaj AasmaanP52100023709 | Lohgaon | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Pankaj Developers, in questions
Does Pankaj Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 33 mo late. Across Maharashtra, 73% kept their date.
How many projects has Pankaj Developers registered with MahaRERA?
3 projects under 6 MahaRERA registrations; 1 completed on MahaRERA.
Does Pankaj Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.