Om Sai Developers
Deedo IDDD-3T4AOf 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 31 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Maruti SankulP52000004469 | Bopele | Certificate Signed | 31 May 2019 | 30 Dec 2021 | +31 mo |
| Shree Krupa SagarP51700018612 | Badlapur | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Gayatri Complex D WingP51700034938 | Shirgaon | Certificate Signed | 31 Dec 2023 | 31 Dec 2027 | +48 mo |
| Sai ArcadeP51700048104 | Badlapur | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
Om Sai Developers, in questions
Does Om Sai Developers finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 31 mo late. Across Maharashtra, 73% kept their date.
How many projects has Om Sai Developers registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Om Sai Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.