Om Sai Developers
Company or firm · 4 projects · 4 MahaRERA registrations
Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+16 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Maruti SankulP52000004469 | Bopele | 2017 | Not reported | 31 May 2019 | 30 Dec 2021 | +31 months |
| Shree Krupa SagarP51700018612 | Badlapur (M Cl) | 2018 | Not reported | 30 Dec 2021 | — | On date |
| Gayatri Complex D WingP51700034938 | Badlapur (M Cl) | 2022 | Not reported | 31 Dec 2023 | 31 Dec 2027 | +48 months |
| Sai ArcadeP51700048104 | Badlapur (M Cl) | 2022 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 48 months, for Gayatri Complex D Wing (P51700034938).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology