Om Sai Developers

Company or firm · 4 projects · 4 MahaRERA registrations

Projects44 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date50%2 of 4 past their proposed date, not extended
Median delay+16 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Maruti SankulP52000004469Bopele2017Not reported31 May 201930 Dec 2021+31 months
Shree Krupa SagarP51700018612Badlapur (M Cl)2018Not reported30 Dec 2021—On date
Gayatri Complex D WingP51700034938Badlapur (M Cl)2022Not reported31 Dec 202331 Dec 2027+48 months
Sai ArcadeP51700048104Badlapur (M Cl)2022Not reported31 Dec 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Maruti Sankul+31 mo
  • Shree Krupa SagarOn date
  • Gayatri Complex D Wing+48 mo
  • Sai ArcadeOn date

Track record notes

  • 2 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 48 months, for Gayatri Complex D Wing (P51700034938).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology