Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

4 of 5 registrations with dates moved or missed their RERA date · months late against the original promise

5 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Om Kavish ExcellencyP99000020278PalgharCertificate Signed30 Dec 202330 Dec 2023On date
Highness HomesP99000049190DhansarCertificate Signed31 Dec 202830 Apr 2029+4 mo
Om Jai Kavish Royal VillasP99000055676PalgharCertificate Signed31 Dec 202930 Apr 2030+4 mo
Golden VillaPR1240002600076PalgharCertificate Signed31 Dec 203130 Apr 2032+4 mo
Hira Prem GardensPM1240002600458PalgharCertificate Signed30 Jun 202930 Oct 2029+4 mo

Om Jai Kavish Realtors, in questions

Does Om Jai Kavish Realtors finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Om Jai Kavish Realtors registered with MahaRERA?

5 projects under 5 MahaRERA registrations; 1 completed on MahaRERA.

Does Om Jai Kavish Realtors have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology