Om Developers Project Green

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
0%Kept RERA date0 of 2 past their proposed date, not extended
+15 moMedian delayvs RERA proposed date · 2 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Tropical Palms Building HP52100005869Pimpri Chinchawad (M Corp.)2017Not reported31 Oct 201831 Oct 2019+12 months
Tropical SquareP52100014854Wakad2018Not reported31 Mar 201930 Sep 2020+18 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Tropical Palms Building H+12 mo
  • Tropical Square+18 mo

Track record notes

  • 0 of 2 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 18 months, for Tropical Square (P52100014854).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology