Oak Constructions
Deedo IDDD-0NNQOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 26 mo late.
Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay26 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases2no insolvency
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| complaint | OAK Med-SquareComplaint CC12501759 | Not on record |
| appeal | OAK Med-SquareAppeal AT01/00553/2026 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| OAK Med-SquareP50500021511 | Nagpur (M Corp.) | Lapsed | 30 Dec 2022 | 31 Dec 2025 | +47 mo* |
| Oak ShantiniketanP50500049041 | Wanjara | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Oak Constructions, in questions
Does Oak Constructions finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 26 mo late. Across Maharashtra, 73% kept their date.
How many projects has Oak Constructions registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Oak Constructions have MahaRERA regulatory cases?
2 regulatory cases name its registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology