Oak Constructions
Company or firm · 2 projects · 2 MahaRERA registrations
Projects22 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date0%0 of 1 past their proposed date, not extended
Median delay+18 movs RERA proposed date · 1 extended
Regulatory cases2MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| OAK Med-SquareP50500021511 | Nagpur (M Corp.) | 2019 | Lapsed | 30 Dec 2022 | 31 Dec 2025 | +36 months |
| Oak ShantiniketanP50500049041 | Nagpur (M Corp.) | 2023 | Not reported | 31 Dec 2027 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 0 of 1 registration whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 36 months, for OAK Med-Square (P50500021511).
Regulatory cases across projects
- complaintComplaint CC12501759 · OAK Med-Square · P50500021511
- appealAppeal AT01/00553/2026 · OAK Med-Square · P50500021511
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology