Niwas Enterprises
Deedo IDDD-20QGOf 11 registrations whose promised date has arrived, 7 kept it (64%). The rest ran a median 5 mo late.
Delivery record
8 of 15 registrations with dates moved or missed their RERA date · months late against the original promise
Show all 15 registrations
15 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Parvati VandanP52100014273 | Pune (M Corp.) | Certificate Signed | 31 Jan 2021 | 31 Jan 2021 | On date |
| ManasP52100017403 | Parvati | Certificate Signed | 1 Jun 2022 | 1 Jun 2022 | On date |
| Dashabhuja C-Op Housing Society -Soudnya BuildingP52100021716 | Parvati | Certificate Signed | 15 Apr 2023 | 15 Apr 2023 | +43 mo* |
| 1976 Sadashiv PethP52100023496 | Sadashiv Peth | Certificate Signed | 15 Nov 2023 | 15 Nov 2023 | On date |
| Suhasini ChsP52100025292 | Parvati | Certificate Signed | 1 Jun 2024 | 1 Jun 2024 | On date |
| Niwant ApartmentP52100027886 | Parvati | Certificate Signed | 1 Dec 2023 | 1 Dec 2023 | On date |
| Dashbhuja Ganesh Sahakari Gruhrachana Maryadit - VrushaliP52100029230 | Parvati | Certificate Signed | 1 Jun 2023 | 1 Jun 2023 | On date |
| Dhananjay ApartmentP52100032511 | Erandwana | Certificate Signed | 1 Dec 2025 | 1 Dec 2025 | +11 mo* |
| Nandadeep Co-Operative Housing SocietyP52100045740 | Parvati | Certificate Signed | 1 May 2026 | 1 May 2026 | On date |
| Hari Vitthal ApartmentsP52100046938 | Pune (M Corp.) | Certificate Signed | 1 Jun 2026 | 1 Oct 2026 | +5 mo* |
| Swati ApartmentP52100048185 | Parvati | Certificate Signed | 1 Dec 2025 | 1 Dec 2025 | +11 mo* |
| Durga ApartmentP52100053754 | Parvati | Certificate Signed | 1 Jan 2027 | 1 May 2027 | +4 mo |
| Suhasini CHSP52100055445 | Parvati | Certificate Signed | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
| Mrunmayee CHSPR1260002501308 | Kothrud | Certificate Signed | 1 Sep 2029 | 1 Jan 2030 | +4 mo |
| Smita ApartmentPR1260002501330 | Parvati | Certificate Signed | 1 Sep 2029 | 1 Jan 2030 | +4 mo |
Show all 15 registrationsShow fewer
Niwas Enterprises, in questions
Does Niwas Enterprises finish projects on time?
Of 11 MahaRERA registrations whose promised completion date has arrived, 7 kept it (64%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Niwas Enterprises registered with MahaRERA?
15 projects under 15 MahaRERA registrations; 7 completed on MahaRERA.
Does Niwas Enterprises have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.