Nirman Square Llp

Deedo IDDD-63A7

None of 3 registrations has reached its promised completion date yet.

Projects23 RERA registrations
Kept RERA dateNone due yetMaharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record148registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Astoria RoyalsP52100047031RavetCertificate Signed30 Sep 202730 Jan 2028+4 mo
Astoria RoyalsP52100048260RavetCertificate Signed30 Sep 202830 Jan 2029+4 mo
Nirman Royals Comm buildingP52100048298RavetCertificate Signed31 Dec 202630 Apr 2027+4 mo

Nirman Square Llp, in questions

Does Nirman Square Llp finish projects on time?

None of its 3 MahaRERA registrations has reached its promised completion date yet.

How many projects has Nirman Square Llp registered with MahaRERA?

2 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.

Does Nirman Square Llp have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.