Nirman Properties
Company or firm · 3 projects · 3 MahaRERA registrations
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date33%1 of 3 past their proposed date, not extended
Median delay+8 movs RERA proposed date · 2 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| One MallP52100002399 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Akash Raj Phase OneP52100002839 | Pimpri Chinchawad (M Corp.) | 2017 | Not reported | 31 Dec 2017 | 31 Aug 2018 | +8 months |
| Akash RajP52100027950 | Pimpri Chinchawad (M Corp.) | 2021 | Not reported | 30 Jun 2023 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 3 registrations whose RERA proposed completion date has passed was never extended beyond it.
- Longest extension on record: 12 months, for One Mall (P52100002399).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology