Niraj Kumar Associates Pvt Ltd
Company or firm · 7 projects · 7 MahaRERA registrations
7Projects7 RERA registrations
0Completedas reported on MahaRERA project pages
43%Kept RERA date3 of 7 past their proposed date, not extended
+7 moMedian delayvs RERA proposed date · 4 extended
0Regulatory casesMahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Mont Vert VelocityP52100001973 | Pashan | 2017 | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 months |
| Mont Vert AvionP52100002448 | Pashan | 2017 | Certificate Signed | 31 Dec 2017 | 31 Jul 2018 | +7 months |
| MontclaireP52100010610 | Pashan | 2017 | Certificate Signed | 30 Dec 2023 | 25 Dec 2024 | +12 months |
| Mont Vert Grande Plot 4 Bldg DP52100020690 | Pashan | 2019 | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | On date |
| Mont Vert Grande Bldg Type G plot 2P52100020880 | Pashan | 2019 | Certificate Signed | 30 Apr 2024 | 30 Apr 2024 | On date |
| Mont Vert Kingstown Sector 1 Commercial WingP52100026359 | Mulshi | 2020 | Certificate Signed | 30 Jun 2024 | 29 Jun 2025 | +12 months |
| Mont Vert Kingstown Sector 1 Residential WingsP52100026366 | Bhugaon | 2020 | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 7 registrations whose RERA proposed completion date has passed were never extended beyond it.
- Longest extension on record: 12 months, for Mont Vert Velocity (P52100001973).
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology