RegisteredRevised date passed1 extensionMahaRERA status: Certificate Signed

P52100002448

Mont Vert Avion · Pashan, Pune · Niraj Kumar Associates Pvt Ltd

Promised for 31 Dec 2017, extended once to 31 Jul 2018 — and that date has passed without the project marked complete on MahaRERA.

8 years and 10 months past the original promise today.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 31 Dec 2017 to 31 Jul 2018 (1 extension certificate on record).
  • Risk: The latest completion date on record, 31 Jul 2018, has passed.
  • Clear: Not on MahaRERA's deregistered, revoked, abeyance or insolvency lists.

Documents 2

Registration certificate1 Aug 2017View
Extension certificate20 Feb 2018View

Orders 0

No MahaRERA order or list names this number.

Questions about P52100002448

Is Mont Vert Avion delayed?

Yes. MahaRERA records a promised completion of 31 Dec 2017, revised to 31 Jul 2018, which has passed, and the project is not marked complete.

How many extensions has it had?

Deedo holds 1 extension certificate for P52100002448. The completion date moved from 31 Dec 2017 to 31 Jul 2018.

Who is the promoter?

MahaRERA records Niraj Kumar Associates Pvt Ltd as the promoter of P52100002448.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P52100002448.

Answers are generated from the record.

Data through28 Oct 2026, 03:27SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology