Nemi Buildcon

Company or firm · 2 projects · 2 MahaRERA registrations

2Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+24 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Nitya DarshanP99000014653Mahim2017Not reported31 Mar 2019—On date
Nitya SamarpanP99000017114Palghar2018Not reported30 Dec 202131 Dec 2025+48 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Nitya DarshanOn date
  • Nitya Samarpan+48 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 48 months, for Nitya Samarpan (P99000017114).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology