Narang Realty Private Limited
Deedo IDDD-D6KYNone of 5 registrations has reached its promised completion date yet.
Delivery record
3 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Narang PrivadoP51700050065 | Thane (M Corp.) | Certificate Signed | 31 Mar 2028 | 31 Jul 2028 | +4 mo |
| Narang PrivadoP51700054336 | Thane (M Corp.) | Certificate Signed | 31 Dec 2028 | 31 Dec 2028 | On date |
| Narang PrivadoP51700077946 | Thane (M Corp.) | Certificate Signed | 31 Mar 2029 | 31 Mar 2029 | On date |
| Narang ValoraPR1180002600544 | Goregaon | Certificate Signed | 31 Dec 2031 | 30 Apr 2032 | +4 mo |
| Narang CastellaPR1180002600545 | Bandra | Certificate Signed | 31 Mar 2032 | 31 Jul 2032 | +4 mo |
Narang Realty Private Limited, in questions
Does Narang Realty Private Limited finish projects on time?
None of its 5 MahaRERA registrations has reached its promised completion date yet.
How many projects has Narang Realty Private Limited registered with MahaRERA?
3 projects under 5 MahaRERA registrations; 0 completed on MahaRERA.
Does Narang Realty Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.