Deedo IDDD-Z4PTOf 1 registration whose promised date has arrived, 1 kept it (100%).
Delivery record
None of 1 registration with dates has moved or missed its RERA date
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nandini Orchid Phase 1P52100014245 | Wadki | Certificate Signed | 9 May 2019 | 9 May 2019 | On date |
Nandini Group Promoters And Builders, in questions
Does Nandini Group Promoters And Builders finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Nandini Group Promoters And Builders registered with MahaRERA?
1 project under 1 MahaRERA registration; 1 completed on MahaRERA.
Does Nandini Group Promoters And Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.